General contractor of the construction «Arena Omsk» - LMS Group of Companies - executes the device of the reinforcing frame, concrete covers of columns and walls from the second to the sixth floor simultaneously on all sections. A concrete roof covering the roof of the main building is being built - the highest level at which construction work is carried out exceeds 32 meters.
At the same time, LMS specialists continue to concrete the bearing beams and mount the stands. As well as the laying of internal engineering networks and partitions on the first, second and third floors.
The builders construct metal-working checkpoints for spectators, as well as entry points for sports teams and freight transport.
The construction of the parking ground for the subsequent installation of the asphalt covering is under way.
LMS group of companies, confirming its reputation as a reliable general contractor, satisfies its obligations to customers on time, who are satisfied with it, trust us again to implement their projects.