In the terminal building, interior finishing works are actively on-going - plastering, ceiling, tiling works. Constructors install doors, partitions,disassembling the necessary structures.
The electrical installation work of the facility is 90% complete - workers are laying cable structures, installing panel panels.
Mechanical works are also in the final stage: a ventilation trunk was installed, insulation works were carried out, a heating and cooling system was installed, sewer and water pipes were proved-out.
Heat insulation of the terminal building roof continues.
In August, fire safety systems were installed: fire cabinets and a radiator, systems of annunciation and management of human evacuation at fire.
According with documentation, the final completion of all types of work is planned no later than October 31, 2020.
Project characteristics: