Dynamics of work on the construction of Airport Voronezh

22.06.2023

The general contractor, LMS Group of Companies, continues to build a new terminal complex of domestic air lines of the Peter I Voronezh International Airport at a high pace.

By the second decade of June, the builders had completed roofing work by 75%, and facade work by 41%. The stained glass windows on the facade of the new terminal building are 75% made, and the sandwich panels are 100% made.

Finishing works are underway in the terminal: plastering of walls and partitions, as well as putty are 100% completed.
The installation of power supply systems, automatic fire extinguishing systems, ventilation, refrigeration, and a set of technical safety equipment is underway. The specialists of the general contractor are laying engineering networks.

The landscaping of the Airport territory was completed by 27%.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers qualitatively and on time, who again entrust us with the implementation of their projects.

Dynamics of work on the construction of Airport Voronezh-photo-1 Dynamics of work on the construction of Airport Voronezh-photo-2 Dynamics of work on the construction of Airport Voronezh-photo-3 Dynamics of work on the construction of Airport Voronezh-photo-4 Dynamics of work on the construction of Airport Voronezh-photo-5 Dynamics of work on the construction of Airport Voronezh-photo-6