Dynamics of work on the reconstruction of Roshchino airport in July

27.07.2023

The LMS Group of Companies, the general contractor, demonstrates the dynamics of the phased reconstruction of the existing terminal complex of international/domestic air lines of Tyumen International Airport (Roshchino).

At the moment, the following works are being carried out at the facility:

  • 25,000 m3 of soil has been developed – 95% of the total volume.
  • The construction of free-standing foundations is 90% completed.
  • The basement foundation is 100% complete%.
  • The vertical structures of the basement are 85%.
  • The installation of the floor slab at the level of -0.150 is completed by 48%.
  • The device of vertical structures above the -0.150 mark is made by 8%.
  • Laid concrete mix in the volume of 3,458 m3 – 32% of the total volume.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers who entrust us with the implementation of their projects again qualitatively and on time.