Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July

05.07.2024

The General Contractor LMS Group of Companies at a high pace continues the construction of the fifth quarter of the Residential complex «Ostrov» (building 1-8) in Moscow with a two-level underground parking lot.

Builders are completing roofing work - 92% have been completed. Heating systems have been installed by 70%, water supply by 95%, ventilation by 81% and air conditioning by 85%. The installation of sewerage and sanitation has been completed by 97%.

A vertical transport has been installed for the facade with composite panels, which currently accounts for 65% of the total volume. The installation of translucent structures was 57%.

The general contractor completed the in-house electrical work by 52%, the installation of low-current systems by 53%.

Finishing works are underway – 44% have been completed. Landscaping of the interior of the facility has begun.

A total of 1,374 professional workers, not including engineers, are involved at the site.

The customer of the project is Donstroy LLC.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-1 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-2 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-3 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-4 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-5 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-6 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-7 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-8 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-9 Dynamics of construction of the 5th quarter of the residential complex «Ostrov» in July-photo-10