The general contractor LMS Group of Companies continues to implement the new Multifunctional complex Kuzminki in Moscow at a high pace.
The progress of work at the facility exceeded 17%. Monolithic works were carried out in the volume of 17,400 m3. Waterproofing of monolithic structures is ready on an area of 15,520 m2.
LMS specialists have already completed concreting of the floor slab and vertical structures of the first floor of the 3rd block, concreting of columns and floor slabs of the second floor of the 2nd block.
At the moment, the following works are continuing at the site:
The facility employs 393 specialists, including IT specialists.
The customer of the project is AStrade Group LLC.