The general contractor LMS Group of Companies is proceeding at a high pace the construction of a new airport terminal complex for domestic air lines of the Mineralnye Vody International Airport.
Builders are installing translucent exterior facades, and installing curved frames made of high-strength aluminum alloy with tempered laminated glass glazing. A volume of 4000 m2 was completed. Roof installation works are also being carried out.
The general contractor has installed all escalators, and work is underway to install elevators.
The installation of screeds and concrete floors has been fully completed at the facility.
The interior decoration of public and technical areas on airport is being carried out:
Work on the installation of internal engineering systems is in full swing:
Work is underway on the installation of internal electrical systems, perforated trays, cables, lamps, transformers and other equipment.
The installation of a block-modular boiler house has been completed, equipment has been installed, commissioning is being carried out, and preparations for the heating season are underway.
The construction of buildings and structures has been fully completed:
Builders are working on the landscaping of the territory: laying asphalt, installing curbs and street lighting.
There are 525 specialists working at the facility. 40 units of special equipment are also involved.
Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.