The general contractor LMS Group of Companies has successfully completed the monolithic structures of the underground part.

LMS builders continue to conduct active work on:
— Monolithic structures — 65% completed.

The construction site employs 1,250 workers, including engineers.

The customer of the project is LLC «Donstroy».

Confirming the reputation of a reliable general contractor, LMS Group qualitatively and on time fulfills its obligations to customers who trust us to implement their projects again.