Dynamics of construction of the residential complex «Ostrov» in Moscow

02.02.2024

The LMS Group of Companies, the general contractor, continues to build the fifth quarter of the Ostrov Residential Complex (Building 1-8) in Moscow with a two-level underground parking at a high pace.

The installation of the main monolithic structures of the above-ground part of the buildings has been completed.

Work is underway on the installation of:

  • exterior walls made of aerated concrete blocks — 99% (+ 9%) completed;
  • interior walls made of aerated concrete blocks — 99% (+ 9%) completed;
  • facades — 34% completed (+ 8%);
  • translucent structures — 5% (+ 1%) completed;
  • internal engineering systems — 23% (+ 1%) completed;
  • roofs — 74% completed (+ 2%).

The interior decoration of the buildings continues — 25% (+ 1%) has been completed.

In total, 915 professional workers, including engineers, and 12 pieces of equipment are involved at the site.

The customer of the project is Donstroy LLC.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

Dynamics of construction of the residential complex «Ostrov» in Moscow-photo-1 Dynamics of construction of the residential complex «Ostrov» in Moscow-photo-2 Dynamics of construction of the residential complex «Ostrov» in Moscow-photo-3 Dynamics of construction of the residential complex «Ostrov» in Moscow-photo-4 Dynamics of construction of the residential complex «Ostrov» in Moscow-photo-5