Construction dynamics of Symvol residential complex in November

19.11.2021

Construction and installation work is underway at the site of buildings 16-18 of the Symvol residential complex in Moscow. LMS specialists carry out the installation of reinforced concrete structures.

The following types of work are performed:

  • Pouring the foundation (93% ready).
  • Completed work on the horizontal waterproofing.
  • Installation of vertical waterproofing is completed by 30%.
  • Backfilling of the pit sinuses continues.
  • Dismantling of the spacer systems of the foundation pit of the future building is underway.

At the site, work has begun on the construction of brickwork.

Construction dynamics of Symvol residential complex in November-photo-1 Construction dynamics of Symvol residential complex in November-photo-2 Construction dynamics of Symvol residential complex in November-photo-3 Construction dynamics of Symvol residential complex in November-photo-4 Construction dynamics of Symvol residential complex in November-photo-5 Construction dynamics of Symvol residential complex in November-photo-6