The readiness of the Arena Omsk exceeds 63%

02.03.2022

The construction of the Multifunctional Sports Complex Arena Omsk continues, the level of technical readiness of the object exceeds 63%.

  • The specialists of Limak Marsh Group of Companies (the general contractor) are completing the installation of the façade metal structures and interior partitions.
  • The finishing of the premises is in progress.
  • The assembling of the stained-glass window of the central facade and the installation of window units have started.
  • The mounting of the external and internal utility networks is going on.
  • The preparatory works for the installation of the engineering systems are finishing in the bowl.

More than 1200 specialists of the general contractor are engaged at the site, including engineering manpower.

Living up its reputation of a reliable general contractor, LMS Group of Companies fulfills its obligations to customers up to the highest standard of performance and in due time, while the finally convinced customers trust us again to implement their projects.

The readiness of the Arena Omsk exceeds 63%-photo-1 The readiness of the Arena Omsk exceeds 63%-photo-2 The readiness of the Arena Omsk exceeds 63%-photo-3 The readiness of the Arena Omsk exceeds 63%-photo-4 The readiness of the Arena Omsk exceeds 63%-photo-5 The readiness of the Arena Omsk exceeds 63%-photo-6 The readiness of the Arena Omsk exceeds 63%-photo-7 The readiness of the Arena Omsk exceeds 63%-photo-8