The general contractor, the LMS Group of Companies, is rapidly building a new airport complex at Magadan International Airport.
The day before, the construction site was inspected by the governor of the Magadan region, Sergey Nosov, noting: «The general Contractor is working with proper quality, the excavation stage has almost been completed.»
The project manager Ilhan Musa Ozkoc reported to the governor that the outdoor networks are ready by 60%, and the parking lot will be asphalted this season. The work is going according to plan – in 2 shifts without breaks.
The following works are being carried out at the construction site:
The purchase and delivery of construction materials to the facility continues.
343 specialists, including IT specialists, are involved at the site.
Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers who entrust us with the implementation of their projects again qualitatively and on time.