iMAll Esplanada put into operation

16.02.2022

Today, iMALL Esplanada in Perm received the Act of commissioning of the object with all permits for the opening of the shopping center.

The first phase of construction included the construction of a shopping and entertainment center with a nine-screen movie theater and an amusement park for children, a fashion gallery, a restaurant area, and a parking lot for 530 cars. A parking lot for 1,200 cars is planned to be opened during all phases of the project construction.

About the project:

  • Customer of the project – Prospect Group LLC
  • General contractor – LMS LLS
  • Implementation period – April 2020 - February 2022.

Specifications of iMAll Esplanada:

  • The area of the building – 87,000 m².
  • Built-up area – 16,000 m².

Timeline of the iMAll Esplanade project

September 2020

The general contractor's specialists were performing monolithic works of the zero cycle, 45% completed. Brickwork has begun.

iMAll Esplanada put into operation - Photo 1October 2020

Presented a 3D model and BIM model of iMAll Esplanada.

Works on the construction of the underground parking were carried out.

iMAll Esplanada put into operation - Photo 2

November 2020

88% of the work on the walls, reinforcement, formwork and slab monolithic construction at the 5.750-meter mark was completed. Construction was performed at 11.6 m and 17.9 m for the second and third floors of the multifunctional center.

iMAll Esplanada put into operation - Photo 3

iMAll Esplanada put into operation - Photo 4

December 2020

The installation of steel structures at the site was started.

iMAll Esplanada put into operation - Photo 5

February 2021

Monolithic works are completed by 93%: monolithic slabs are almost fully installed (94%) and vertical structures - columns and walls on the first-fourth floors (85%).

Steelwork assembly works were in progress: superstructures, roof trusses, beams and roof trusses. Specialists continued to install brick partitions, heating and ventilation systems, and insulation.

iMAll Esplanada put into operation - Photo 6

April 2021

The heating system was half done, the sewer and water systems were one-third done. The concrete work was fully completed. At the + 30.00 mark, the monolithic beams for the steelwork were installed.

More than two-thirds of the steelwork at the three major work areas was installed. The metal staircases were fully installed. The specialists continued the installation of the sandwich panels and the roof profiled sheeting.

The general contractor's specialists continued mechanical and electrical work on the project. The heating system was half finished. The water supply and sewerage systems were almost one third completed, the ventilation system was 42% ready.

iMAll Esplanada put into operation - Photo 7

iMAll Esplanada put into operation - Photo 8

May 2021

The general contractor has completed the monolithic work on the building. From ground level it is 4 floors up and 3 floors down. The façade of the building was covered with sandwich panels at 20%.

iMAll Esplanada put into operation - Photo 9

iMAll Esplanada put into operation - Photo 10iMAll Esplanada put into operation - Photo 11

June 2021

LMS specialists continued decorating the facade of the iMAll Esplanade building: sandwich panel installation work was half done. Mechanical work was 90% complete and the electrical system was more than 50% complete.

July 2021

1,104 tons of steel structures were installed. 95% completion rate.

Mounting of the coverings and facings of the building was finished (99%). The installation of the facade sandwich panels was also in progress (95%).

Specialists installed almost half of the 19 elevators.

iMAll Esplanada put into operation - Photo 12

iMAll Esplanada put into operation - Photo 13

August 2021

On the construction site, LMS specialists have completed the installation of steel structures of the building (99%). More than 1210 tons of steel structures were installed.

The organization of stable power supply of the premises was actively carried out on the site. For electric cable laying have been used over 121 000 linear meters, readiness of this type of work is 68%. The installation of water supply and indoor sewage pipes and heating systems are 80% complete. 11 out of 19 elevators, 1 escalator and 2 moving walkways were installed at the site.

iMAll Esplanada put into operation - Photo 14

iMAll Esplanada put into operation - Photo 15

September 2021

At this stage of works, 100% of all steel structures were installed, the readiness of the roof installation was 100%. The installation of profiled sheeting was 100% complete.

The installation of facade glazing on the area of 2,550 m² was performed, the readiness of the works was 75%. Ventilation system was 88% ready, heating system was 92% ready, cooling system and fire system were 94% ready.

iMAll Esplanada put into operation - Photo 16

iMAll Esplanada put into operation - Photo 17

October 2021

The completion of work on the facade glazing was 97%. Finishing work inside the building was performed on an area of 16,793 m². Walls made of aerated concrete blocks were erected on the site of the future cinema halls. The total area of the works was 6,864 m², the works are half completed.

All 19 elevators and 4 moving walkways were installed, as well as 4 escalators out of 14.

Improvement of adjoining territory was completed: asphalt concrete pavement and paving slabs were laid.

iMAll Esplanada put into operation - Photo 18

November 2021

All works on installation of steel structures, installation of the roof of the building and installation of profiled sheeting are completed on the site. Finishing works: 97% readiness of finishing of public areas. Installation of ventilation system, heating system and cooling system is close to 97% readiness.

iMAll Esplanada put into operation - Photo 19

iMAll Esplanada put into operation - Photo 20iMAll Esplanada put into operation - Photo 21

December 2021 - January 2022

The process of obtaining compliance of the facility with the requirements of the project documentation to the Inspectorate of State Construction Supervision was started. Work was carried out to eliminate the comments.

iMAll Esplanada put into operation - Photo 22

February 2022

The first phase of construction of the iMAll Esplanada in Perm was completed. According to the results of the final inspection, a conclusion of compliance of the facility with the requirements of the project documentation was obtained.

The object was put into operation on February 16, 2022.