Results of the first year of reconstruction of Roshchino airport in Tyumen

21.06.2024

General Contractor LMS Group of Companies summarizes the results of the first year of the phased reconstruction of the existing airport terminal complex of international/domestic air lines of Tyumen International Airport (Roshchino).

Exactly one year has passed since the laying of the «Time Capsule», when the official start was given to the construction of a new passenger terminal at Roshchino airport. During this time, the installation of metal structures, masonry of brick partitions and aerated concrete blocks of the first floor were completely completed at the facility. 

A significant part of the work on the installation of internal engineering networks has been completed and work on the interior decoration of the premises continues.

At the moment, builders are engaged in facade glazing and roofing work. 7 elevators have already been installed, as well as 3 escalators. The scope of work of the 1st stage is about 19 thousand square meters.

During the work on the first stage, 2 new teletraps, a new first-aid post, a full-fledged mother and child room will be erected, passenger waiting areas will be increased, a new baggage claim hall for domestic flights and a high-comfort hall.

A new look of the terminal will also be laid, including a solid glass central facade and a new roof shape in the form of a «wing». After completion of work on all three stages of construction, the terminal's capacity will increase from 600 passengers per hour to 1,940 passengers per hour.

The planned completion date of the 1st stage is 31.12.2024.

436 specialists of the general contractor, including engineering and technical staff, are involved at the site.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-1 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-2 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-3 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-4 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-5 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-6 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-7 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-8 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-9 Results of the first year of reconstruction of Roshchino airport in Tyumen-photo-10