90 days of construction of the new terminal at Khabarovsk airport

02.12.2021

Exactly three months have passed since the beginning of the construction of the new Khabarovsk Airport Terminal of International Airlines.

What happens at the construction site?

  • Completed work on the last stage of the removal of communications from the construction area.
  • The grillage is being poured – 109 out of 128 have been worked out, 706 m3 of concrete have been poured.
  • The pouring of the vertical structures of the 1st floor continues, 253 m3 of concrete was produced out of 461 m3.
  • Work is underway on the waterproofing of the grillage, as well as backfilling of the pit sinuses. Produced 12,000 m3 from 15,000 m3.
  • The floor slab is being poured – 510 m3 of concrete was produced out of 1,332 m3.
  • The pouring walls and basement floor slabs has been completed – 658 m³ of concrete has been produced.
  • Pouring of сoncrete foundation has begun in the basement floor. The floor slab will be reinforced with further concrete pouring soon.
  • Preparatory work has begun on pouring the floor slab on the first floor.
  • There are 373 people on the construction site.

This is already the second project of joint cooperation with the customer — JSC Khabarovsk International Terminal. The first project was the construction of a passenger terminal for domestic airlines at Khabarovsk International Airport.

90 days of construction of the new terminal at Khabarovsk airport-photo-1 90 days of construction of the new terminal at Khabarovsk airport-photo-2