LMS has completed the facade cladding of the new Magadan airport by 35%

19.04.2024

The General Contractor LMS Group of Companies is proceeding at a high pace the construction of a new airport complex at Magadan International Airport .

The builders have completed 35% glazing of the facade. At the same time, roofing, street and interior works are carried out. The construction of partitions, the laying of communications, and the rough finishing of the premises are continuing.

Now about everything in order:

  • The installation of metal structures of the coating is 100% complete
  • Installation of half-timbered metal structures - 85 %
  • Profiled flooring - 100%
  • The installation of a soft roof is 85% complete 
  • Installation of sandwich panels for 85%
  • Installation of translucent structures - 35%
  • Partition made of wall blocks - 89%
  • Partitions according to the Knauf system with 382 of AQUAPANEL plates on 38%
  • The screed made of cement-sand mortar is made of 36%
  • Plaster walls - 34%
  • Installation of heating systems - 34%
  • Installation of ventilation systems - 45%
  • Outdoor electric lighting 23%
  • The installation of household sewerage, heating networks and cable trays is being completed.

475 specialists, including engineering and technical staff, are involved at the site. Large construction equipment is working.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

LMS has completed the facade cladding of the new Magadan airport by 35%-photo-1 LMS has completed the facade cladding of the new Magadan airport by 35%-photo-2 LMS has completed the facade cladding of the new Magadan airport by 35%-photo-3