The General Contractor LMS Group of Companies is proceeding at a high pace construction of a new airport terminal complex for domestic air lines of the Mineralnye Vody International Airport.
Monolithic works of the building frame are 96% completed, 21,200 m3 of concrete were used. Work continues on the construction of vertical reinforced concrete structures - columns and walls. Monolithic stairs are 70% complete.
The installation of metal structures is on schedule - 80% of the required volume of metal in the amount of 816 tons has been delivered to the facility.
Work has begun on the roofing of corrugated board. Finishing works are continuing.
The 1st floor is 96% completed (294 m3)
The 2nd floor is 93% completed (502.96 m3)
0-floor (basement) 96% completed (82 m3)
1st floor is completed on 81 (53.50 m3)
The 2nd floor is 100% completed (109.75 m3)
There are 723 specialists working at the facility, including IT specialists. 49 units of specialized equipment are involved, including 2 tower cranes.
Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.