The General Contractor LMS Group of Companies is proceeding at a high pace the construction of a new airport complex at Magadan International Airport.
Specialists are completing the installation of the hinged facade - 98% has been completed.
The following works have been completed completely at the facility (100%):
Workers are currently finishing the installation of porcelain stoneware (95% completed), are engaged in the installation of internal doors (90% completed) and furniture (60% completed), as well as the installation of plumbing equipment (97% completed). The installation of internal stained glass windows in the form of glass partitions and fences is 85% complete. The installation of mechanical and electrical systems is 95% complete.
Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again