LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody

10.06.2024

The General Contractor LMS Group of Companies is proceeding at a high pace the construction of a new airport terminal complex for domestic air lines of the Mineralnye Vody International Airport.

The builders completed all the monolithic work on the construction of the building frame, using more than 15 thousand m3 of concrete. Work on the installation of metal structures of the Airport terminal is being completed - all metal trusses have been installed and vertical and horizontal connections are fully secured. In total, 1.1 thousand tons of metal were installed.

The general contractor installs the exterior translucent facades, conducts the installation of curved frames made of high-strength aluminum alloy with tempered laminated glass glazing. The nodes of the roof joining to the facades are also performed.

The roof of the new Airport is completely covered with a metal profile, which allows for finishing work inside the terminal.

Finishing works are underway at the facility:

  • The work on the installation of internal partitions made of gas block and brick has been completed by 90%.
  • The installation of partitions using the Knauf system of gypsum and cement-mineral slabs on a metal frame is also being completed.
  • The work on the installation of high-quality plaster has been completed by 70%, it is more than 15 thousand m2.
  • The installation of cement-sand screeds is 90% ready (18.5 thousand m2).
  • Work has begun on filling the walls and laying porcelain stoneware.
  • Work on the installation and installation of internal engineering systems is also carried out in accordance with the schedule.

The work on the foundations of the block-modular boiler house has been fully completed. The installation of the boiler house itself will be completed at the end of this month or the beginning of next month.

Tests of fire tanks with water have been completed, and backfilling with soil is underway.

Builders are carrying out construction and installation work of the pumping station, including finishing work. The equipment is being installed and put into operation. The temporary command and control center has been fully put into operation.

Landscaping at the facility: the foundation is being prepared for laying asphalt concrete mix, installing a curb stone, laying paving slabs.

There are 646 people involved at the facility, taking into account engineers. 45 units of special equipment are also involved.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-1 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-2 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-3 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-4 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-5 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-6 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-7 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-8 LMS has completed monolithic work on the construction of the frame of the new building of the Airport MinVody-photo-9