The progress of reconstruction of the Roshchino Airport in Tyumen in February

28.02.2024

The LMS Group of Companies, the General contractor, demonstrates the dynamics of the phased reconstruction of the existing airport terminal complex of international/domestic air lines at Tyumen International Airport (Roshchino).

Currently completed general construction works:

  • Monolithic works are 100% completed.
  • The installation of the metal structure is 98% complete.

Network work is being carried out (electromechanical work):

  • Electric trays - 71 completed%
  • Automatic fire extinguishing system - 47% completed.
  • Duct system - 32% completed.
  • Water supply and sewerage system - 11% completed.

Finishing and facade works are being carried out:

  • The finishing work was completed by 17%.
  • The facade work was completed by 11%.

315 specialists, including IT specialists, are involved at the site.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

The progress of reconstruction of the Roshchino Airport in Tyumen in February-photo-1 The progress of reconstruction of the Roshchino Airport in Tyumen in February-photo-2 The progress of reconstruction of the Roshchino Airport in Tyumen in February-photo-3 The progress of reconstruction of the Roshchino Airport in Tyumen in February-photo-4 The progress of reconstruction of the Roshchino Airport in Tyumen in February-photo-5 The progress of reconstruction of the Roshchino Airport in Tyumen in February-photo-6