The General contractor LMS Group of Companies demonstrates the dynamics of the phased reconstruction of the existing airport terminal complex of international/domestic air lines at Tyumen International Airport (Roshchino).
The construction progress of the new Roshchino Airport exceeded 76%.
The facade work is 95% complete. The installation of elevators and escalators is 100% complete (11 elevators and 7 escalators have been installed). Landscaping works and access roads to the AVK building are 100% completed. The finishing work was completed by 76%. The installation of glass partitions is 80% complete. The roofing works of the new AVK are 100% completed. Electrical work was completed by 55%, and mechanical work by 71%.
473 specialists, including engineering and technical staff, are involved at the site. 14 units of construction equipment are involved.
Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.