The construction progress of the new Magadan Airport exceeded 82%

17.09.2024

The general contractor, LMS Group of Companies, is rapidly building a new airport complex at Magadan International Airport.

The construction progress of the new Magadan Airport exceeded 82%.

The builders are completing the electromechanical work. For example, the installation of thermal networks of transformer substations is 100% complete, and automatic fire extinguishing systems are 97% complete.

The facade work is 100% completed. The facade is made of transparent glazing, which gives airiness and lightness to the building. 

Finishing works are underway at the facility - 80% have been completed. 

The installation of telescopic ladders is completed by 80%, and elevators and escalators by 30%.

The builders have completely completed the laying of asphalt in the parking lot, installed paving stones around the perimeter and are completing the landscaping of the territory.

475 specialists, including engineering and technical staff, are involved at the site. 24 units of construction equipment are involved.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

The construction progress of the new Magadan Airport exceeded 82%-photo-1 The construction progress of the new Magadan Airport exceeded 82%-photo-2 The construction progress of the new Magadan Airport exceeded 82%-photo-3 The construction progress of the new Magadan Airport exceeded 82%-photo-4 The construction progress of the new Magadan Airport exceeded 82%-photo-5 The construction progress of the new Magadan Airport exceeded 82%-photo-6 The construction progress of the new Magadan Airport exceeded 82%-photo-7