Reconstruction of Tolmachevo Airport terminal square

09.07.2019

LLC «LMS» has been awarded as general Contractor for reconstruction of terminal square, engineering infrastructure and utilities of Tolmachevo Airport. The contract was signed on July, 10th, 2019. Works at the site have been started and will be finished according to the schedule at the end of 2019. In the scope of two stages the following works are included:

  • power supply and CCTV cabling - 58 000 m (I stage)/4 000 (II stage);
  • light poles installation - 118 pcs (I stage)/ 32 pcs (II stage);
  • heat supply connection arrangement - more than 4000 m (I stage)/950 m (II stage);
  • domestic and storm water drainage plumbing - 6000 m (I stage)/ 719 m (II stage);
  • landscaping area - 40 000 m2.