The construction of the Arena continues at all sites.
Inside of the building:
The assembly of the grandstands of the first tier has been completed. Work is underway at the level of the second tier.
Internal staircases are being installed, engineering networks are being installed, screed for 1–5 floors.
Internal partitions are mounted on the 1st - 4th floors. At the same time, surfaces are being prepared for finishing on the ground floor.
Outside of the building:
The load-bearing metal structures are being mounted for the first installation of the stained-glass window of the main building. The installation of the roof covering is in progress.
Landscaping:
At the same time, the landscaping of the parking area is being carried out. At two sites, the builders are laying the first layer of asphalt concrete pavement.
The installation of external engineering networks continues: heat supply, sewerage, communication networks, power supply and lighting.