Specialists of the general contractor of the LMS Group of Companies at a high pace construct a new building of the Perm State Art Gallery.
The work was completed by 89%. The facility is scheduled to be commissioned in August 2024. At this time, the builders are simultaneously completing work on the letters O, N, C.
Facade and roofing works are 99% completed. The glazing is 99% complete, the installation of composite panels is 85% complete.
The finishing work was completed by 84%. The work on the installation of plaster, screed filling, installation of gas blocks and drywall has been completed. Finishing works have also been carried out in the basement. On the remaining floors, terrazzo tiles are being laid, walls are being painted and wooden panels are being installed.
The external heating, water supply and sewerage networks are 100% complete. The work on the internal mechanical systems has been completed by 90%. 34,000 m2 of air ducts and 6,000 m of fire-fighting water pipes have been installed. The installation of the gas fire extinguishing system is 95% complete.
The work on the electrical systems has been completed by 75%. Work continues on the installation of power supply systems, automation of fire extinguishing systems and a set of technical safety equipment. The landscaping of the territory has been completed by 70%.
Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.