The technical readiness of the Arena Omsk is 50%

30.12.2021

The technical readiness of the Arena Omsk has exceeded 50%.

  • In 2021, the installation of the main structures of the Arena was completed. All 6 floors of the building have been completed, stands and roof have been mounted.
  • The glazing of the inspection pavilions has been completed. An individual heating point was launched. The building is supplied with heat.
  • Warming of the building continues. Metal structures of cold and warm contours of the facade, external and internal engineering networks are being mounted. More than 50% of internal partitions have been installed, finishing works are in progress.
  • Refrigeration equipment for ice preparation was delivered to the site. Supply of ventilation equipment has begun.

During the New Year holidays, a construction of Arena Omsk will continue.

The technical readiness of the Arena Omsk is 50%-photo-1 The technical readiness of the Arena Omsk is 50%-photo-2 The technical readiness of the Arena Omsk is 50%-photo-3 The technical readiness of the Arena Omsk is 50%-photo-4 The technical readiness of the Arena Omsk is 50%-photo-5 The technical readiness of the Arena Omsk is 50%-photo-6 The technical readiness of the Arena Omsk is 50%-photo-7 The technical readiness of the Arena Omsk is 50%-photo-8 The technical readiness of the Arena Omsk is 50%-photo-9 The technical readiness of the Arena Omsk is 50%-photo-10