«Nebo» Shopping Center: 1/5 of the project work is completed

24.02.2021

Project continues to Shopping center «Nebo» in the West of Moscow: one-third completed the construction of walls (29%) and facade (33%).

LMS specialists have almost completed the installation of partitions made of gas block (93%) and brick (80%). The installation of sandwich panels is 65% complete.

Works on finishing of premises are actively promoted: plaster (56%), putty (43%). More than a third of the screed (31%) and the installation of tiles on the floor (35%) were completed. Electrical (11%) and mechanical (15%) work continues.

Recall that the deadline for the completion of the shopping center «Nebo» is September 2021. The customer of the project is the Stolitca Management Management Company.

The LMS Group of companies, confirming its reputation as a reliable general contractor, efficiently and on time fulfills its obligations to customers, who, having made sure of this, trust us again and again to implement their projects. The company's portfolio of implemented projects includes the construction of international airports in Rostov-on-Don, Volgograd, Khabarovsk, Chelyabinsk, as well as other infrastructure facilities in Russia.