Simvol HC Reaches the Twentieth Story

07.06.2022

Specialists of the general contractor (LMS Group) continue construction and installation works according to the approved schedule at the construction site of the 16th to 18th buildings of the Simvol Housing Complex in Moscow.

Builders are currently installing floor slabs and vertical structures on the eleventh story in the 16th building. On the 17th building site, the construction of vertical structures of the fifth story is underway. In the 18th building, builders continue installing floor slabs and vertical structures on the twentieth story. Reinforced concrete works have been completed in the sports and recreation center.

Walls made of aerated concrete blocks are being erected on the seventh story of the 16th, on the eleventh story of the 17th, and on the sixteenth story of the 18th buildings.

LMS specialists continue installing air ducts in the parking lot at the -1st level; work has already been completed on the -2nd level. Cable troughs are also being installed in the parking lot. Installation of a drainage pipe continued at a below zero elevation.

Plastering works are performed on the fifth story of the 17th and on the thirteenth story of the 18th buildings. Rough finishing work continues in the 18th building.

Installation of metal brackets for facade scaffolding has been completed. The scaffolding installation is underway in all building. The facade subsystem is being installed in the 16th and 17th buildings. The heat insulation system is being set up in the 18th building.

Simvol HC Reaches the Twentieth Story-photo-1 Simvol HC Reaches the Twentieth Story-photo-2 Simvol HC Reaches the Twentieth Story-photo-3 Simvol HC Reaches the Twentieth Story-photo-4 Simvol HC Reaches the Twentieth Story-photo-5 Simvol HC Reaches the Twentieth Story-photo-6 Simvol HC Reaches the Twentieth Story-photo-7 Simvol HC Reaches the Twentieth Story-photo-8