LMS installed 4,650 tons of metal structures at the facility in Chernyakhovsk

16.12.2022

The general contractor LMS Group of Companies continues to rapidly implement the Industrial Complex for the production of silicon wafers and photovoltaic converters (PCs) in the Chernyakhovsk Industrial Park. The customer of the project is the ANCHOR plant, which belongs to Unigreen Energy.

More than 4,650 tons of metal structures have been installed in the PC buildings. Roofing works in buildings No. 2 and No. 4 are being completed. Installation of sandwich panels of internal walls and partitions is ready by 24% in building No. 2, by 94% in building No. 4 and by 75% in building No. 10.

LMS specialists are in the process of finishing plastering works. Putty and painting works are ready for 35%, laying ceramic tiles for 65%. The device of the GCL subsystem of building No. 16 is in the active phase, 80% has been completed. Installation of internal and external engineering systems continues.

Landscaping of the territory continues: the installation of the curb stone is completed by 55%, the installation of the foundation for on-site roads by 35%. Work has begun on the installation of running tracks on the roof.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us with the implementation of their projects.

LMS installed 4,650 tons of metal structures at the facility in Chernyakhovsk-photo-1 LMS installed 4,650 tons of metal structures at the facility in Chernyakhovsk-photo-2 LMS installed 4,650 tons of metal structures at the facility in Chernyakhovsk-photo-3 LMS installed 4,650 tons of metal structures at the facility in Chernyakhovsk-photo-4 LMS installed 4,650 tons of metal structures at the facility in Chernyakhovsk-photo-5