Mass Media about us

News
The new terminal of the airport in Novy Urengoy took the first flight

The construction of the terminal lasted exactly two years. The first pile was hammered on December 22, 2020. More than 800 builders and over 30 units of large construction equipment worked at the facility. A boiler house with a capacity of 20 MW was built to service the terminal.

The first test flight to the new terminal landed in Novy Urengoy

Construction of the new passenger terminal began on December 22, 2020. The general contractor of the construction – LMS Company – completed all the planned works in two years.

The new terminal of Novy Urengoy Airport received an opinion on compliance (AIA)

The new passenger terminal of Novy Urengoy Airport has been inspected by the North Ural Department of Rostechnadzor and received an opinion on compliance (AIA) with the requirements of the project documentation. The official start of the construction of the new passenger terminal was given on December 22, 2020. Within two years, the general contractor of the construction – LMS – completed all the necessary amount of construction work. The new airport complex is equipped with modern equipment for servicing passengers and their luggage, escalators, elevators, and a baggage handling system are installed.

Novy Urengoy Airport. From a modest Yagelny to the most modern terminal

The new passenger terminal at Novy Urengoy Airport will be launched on December 25, 2022. Stylized as a traditional dwelling of nomads, the building occupies almost 20 thousand square meters. The new airport complex has many features for the comfort and convenience of passengers, ranging from silent escalators and elevators to telescopic ladders. The building was equipped with a bas-gate system — a warm tunnel for buses located in the terminal, through which passengers will board and disembark on apron buses, which is especially important in the harsh climate of the Far North.

The construction of the frame of the new Perm Gallery building has reached the fourth floor and the roof

By the beginning of December, more than 1,500 tons of metal structures were installed, according to the general contractor of the construction, GC LMS. To better ensure the friction of materials and prevent metal damage, work is underway to tighten high-strength bolts with controlled tension. The backfill of the pit was carried out in the volume of 13 thousand 608 m3.

New Urengoy Airport starts testing new terminal

The first comprehensive test of the new passenger terminal took place at Novy Urengoy Airport. It was attended by airport employees who acted as passengers. In the course of testing, specialists from the air hub's subdivisions practise all the main passenger service processes in the new terminal and check the operability and steady operation of the equipment.

Construction begins on 3rd floor of new airport terminal in Voronezh

The builders have started reinforcing the floor slab of the third floor of the new Voronezh Airport Terminal. In the near future they plan to finish concreting the floor slab and start concreting the vertical structures. In the basement of the future terminal, the construction of partition walls made of aerated concrete blocks has started.

Construction begins on 2 floors of new airport terminal in Voronezh

Builders have started concreting the floor slab of the first floor of the new terminal of Voronezh airport. This was reported by the airport press service on 13 November. Photos and videos of the construction process were published on the Internet. The new terminal is being built by LMS group of companies

New building of Voronezh airport is planned to be completed in 2023

Despite the fact that Voronezh airport has been non-operational for more than eight months and does not bring profit to its owner, the construction of the new airport terminal complex continues on schedule. The construction of the terminal started in January 2022. The customer of the project is the holding «Novaport» which now owns the airport terminal. The general contractor is a group of companies LMS. According to the company, the new terminal with the area of 13,700 square meters will have three floors.

Construction of the passenger terminal at Novy Urengoy airport is nearing completion

The construction of the passenger terminal at Novy Urengoy Airport is nearing completion. The adjacent territory has been landscaped. The work inside the building is in full swing. The workers of the contracting company are working at a rapid pace. They are planning to finish the facade by the end of the week. In total, about 800 people are working at the site.

1.1 tons of metal structures were installed during the construction of the new Perm Gallery

In Perm, builders continue to assemble the frame of the new building of the state art gallery. As of November 3, more than 1,150 tons of metal structures have been installed, this was reported in the Ministry of Construction.

1.1 tons of metal structures were installed during the construction of the new Perm Gallery
Cassation canceled the fine to the general contractor of the construction of iMall «Esplanade»

LMS LLC won the case in the Seventh Court of Cassation of Chelyabinsk for an administrative fine of 300 thousand rubles at the construction of the iMall Esplanada in Perm. This was reported by the company's press service.

The General Contractor of the Perm iMall Esplanada has achieved the cancellation of the fine for dirt

The LMS company, which was previously fined for removing dirt from the construction site of the Perm shopping center «iMall Esplanade», was able to achieve the cancellation of the punishment. The developer challenged the fine of 300 thousand rubles in the Seventh Court of Cassation of Chelyabinsk, told URA.RU in the company.

LMS launched an online broadcast of the construction of the Perm Art Museum

At the beginning of October, the company LMS launched an online broadcast from the site where the construction of the new building of the Perm Art Museum is going on. On the company's website, the progress of the work can be monitored using three cameras.

Russian companies can occupy the niche of foreign contractors

According to Sergey Podolsky, this is a good opportunity for Russian manufacturing companies to occupy the niche of foreign contractors and replace imported materials and equipment with Russian analogues. «Especially since at the moment domestic manufacturers are upgrading their production capacities and are superior to foreign ones in some characteristics,» he said.

The contractor of the Perm Gallery explained his decision not to buy German glass

The Turkish company LMS, which is the contractor of the new building of the Perm Art Gallery, commented on the decision to refuse to buy German stained glass for the glazing of the gallery's facades. LMS's deputy project manager for the Perm gallery, Sergei Podolsky, explained that this was due to the speculative increase in prices for glass panes from Germany and the inability to supply them due to the sanctions.

Dmitry Makhonin checked the progress of priority cultural projects in preparation for the anniversary of Perm

The Governor also inspected the construction site of the Perm Art Gallery building, a facility of about 20 thousand square meters, which will provide all the necessary conditions for the storage and display of the unique collection of art masterpieces. The construction is being carried out by LMS LLC, a contracting organization.

Our new G-Drive Arena from a bird`s eye view

On October 1, the G-Drive Arena Ice Complex, the new home stadium of the Avangard hockey club in Omsk, was opened. The arena was built as part of a public-private partnership between Gazprom Neft, the Governments of the Russian Federation and the Omsk Region.